The design and build contract for the Paphos-Polis Chrysochous road, signed in 2021 under the previous administration, was ended because the contractor chose not to continue, the transport ministry said on Saturday after days of criticism on social media.
The ministry said the contractor made “unjustified and excessive” claims, including asking for €36 million in compensation and a 59-month extension for a project valued at approximately €73 million.
These claims